Construction Update

Courts and fencing are done and waiting for striping, 10.25.2025. Playing by Nov. 7?

(Cick on pics to expand)

Pics left to right, starting at top:

Preparing concrete forms for fences and net posts on 9.16.2025

Fence posts going in to concrete forms on 09.18.2025

Concrete forms for curbing and fenceposts completed on 09.26.2025

Morley & Sons Construction (local firm doing grading and base) on 10.02.2025, preparing for the asphalt pour week of 10/06!

Two pictures of asphalt work going on Monday, 10.06.2025

Asphalt is done (10/7)! Two weeks to cure, add fencing, nets, finish grading.

Asphalt is curing (10/10) and fencing is beginning.

Fencing installation (10/17)

Asphalt is almost cured (10/19) and fencing is continuing.

Next
Next

Here come the courts!